How to run a specific job with two nodes if project is running with four nodes?

Go to data stage manager->open default configuration file->save as with another name by clicking down save button (say sample)->now delete two nodes from sample file->save and close.

Go to data stage designer->open a particular  job ->go to job properties->go to parameters->click on add environment variable ->select APT_CONFIG_FILE->Double click on default value  Choose Sample. Apt->click ok now our required job is run with two nodes